SYNCHRO 4D Pro 2026发布,升级NVIDIA Iray渲染引擎,增强4D协同模拟与资源管理,支持旧版文件兼容,提升施工规划效率与可视化质量。

原始标题:SYNCHRO 4D Pro 2026 (06.05.10.21)

SYNCHRO 4D Pro 2026 (06.05.10.21)

  • 4D 协同模拟:在单一可视界面中并排创建、编辑、分析和管理进度与三维空间模型。
  • 高效资源管理:优化了资源创建向导的响应速度,使分配、筛选和展开操作更加快捷。
  • 渲染引擎升级:集成了更新的 NVIDIA Iray 渲染引擎(版本更新至 2025.0.12),提供更高质量的项目可视化效果。
  • 文件兼容性:支持向前兼容,能够轻松打开和转换旧版本的 .sp 项目文件。
  • 现场与办公室连接:帮助项目团队提前识别冲突、规划运输和临时工作,从而提升安全性与执行效率。

Synchro Systems, a bussines Bentley Systems, is pleased to announce the availability of SYNCHRO 4D Pro 2026 (06.05.10.21) is an advanced software tool to plan, schedule, and manage construction projects in a 4D environment.

Major features
– NVIDIA Iray Upgrade. Updated the integrated NVIDIA Iray rendering engine from version 2021.0.3 to 2025.0.12. Users can benefit from improved compatibility with newer NVIDIA GPUs and rendering improvements available through the Iray functionality exposed in SYNCHRO 4D Pro
– Added additional diagnostic information to help investigate and troubleshoot application responsiveness issues.
Bugs squashed
– Fixed an issue where importing Primavera P6 XML files exported from a P6 database could fail during the import process. This improvement allows supported P6 project data to be imported more reliably using the default import workflow.
– Fixed an issue that could cause SYNCHRO 4D Pro to crash when projects were repeatedly closed and reopened during the same application session.
– Security fixes.

SYNCHRO 4D Pro is an advanced software tool to plan, schedule, and manage construction projects in a 4D environment. Scheduling and planning is critical to safe, efficient, high quality construction. While using 4D, the computer becomes a practice field where sequences, safety, special relationships and more can be viewed and discussed continuously before and throughout the project lifetime. Because SYNCHRO Pro links 3D Resources (human, material, equipment, and space) to the associated schedule tasks, making changes and comparing baselines to alternatives is quick and easy. Testing sequencing and running “What-if” scenarios is highly efficient and engaging. Communications are crystal clear, because you can see each step in the process. Cooperative knowledge sharing creates innovation and unique approaches that build competitive advantage. The result is an efficient, reliable and safe project delivery process that saves time and money. SYNCHRO Pro integrates with Oracle Primavera and other scheduling software but it is a stand-alone CPM scheduling tool and does not depend on importing schedules from legacy software. Whether you like to see the schedule through the model or see the model through the schedule, the ability to visualize your plan while maintaining its integrity allows project delivery performance to consistently and reliably exceed today’s performance standards in an immediate and dramatic way.

Bentley Systems, Inc. is the global leader dedicated to providing architects, engineers, constructors, and owner-operators with comprehensive architecture and engineering software solutions for sustaining infrastructure. Founded in 1984, Bentley has nearly 3,000 colleagues in more than 45 countries, $500 million in annual revenues, and, since 2001, has invested more than $1 billion in research, development, and acquisitions.

官方网站:http://www.bentley.com